Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Passed

Inspection History: TRSP - PIA - AB Placement

Date Description Inspector Results Comments
11/04/2025 TRSP - PIA - AB Placement Passed Three density tests were taken to cover the 3400 linear feet of spine road along Paseo Gran Escalera. Stations 61+00, 50+00, and 39+00 were the testing spots on either side of the center line, and all three tests were greater than 100%. Moisture was also within specification range. The material is black AB.
11/10/2025 TRSP - PIA - AB Placement Passed The entire stretch of Paseo Gran Escalera was string lined for grade starting at station 26+75 to 64+00. There was only one area that needed a little shave of the grade, but the rest was within the specification of .02' above and below established grade. Density tests were taken last week, and all resulted with 100% compaction. Roadway is ready for paving the next three days.
11/13/2026 TRSP - PIA - AB Placement Deferred