Inspection Status: Passed
Inspection History: TRSP - PIA - AB Placement
| Date |
Description |
Inspector |
Results |
Comments |
| 11/04/2025 |
TRSP - PIA - AB Placement |
|
Passed |
Three density tests were taken to cover the 3400 linear feet of spine road along Paseo Gran Escalera. Stations 61+00, 50+00, and 39+00 were the testing spots on either side of the center line, and all three tests were greater than 100%. Moisture was also within specification range. The material is black AB. |
| 11/10/2025 |
TRSP - PIA - AB Placement |
|
Passed |
The entire stretch of Paseo Gran Escalera was string lined for grade starting at station 26+75 to 64+00. There was only one area that needed a little shave of the grade, but the rest was within the specification of .02' above and below established grade. Density tests were taken last week, and all resulted with 100% compaction. Roadway is ready for paving the next three days. |
| 11/13/2026 |
TRSP - PIA - AB Placement |
|
Deferred |
|