Inspection Status: Partial Pass
Inspection History: Grading Progress ENGR
| Date |
Description |
Inspector |
Results |
Comments |
| 06/09/2026 |
Grading Progress ENGR |
|
Partial Pass |
|
| 06/18/2026 |
Grading Progress ENGR |
|
Partial Pass |
to wet to work because of the rain last night.contractor will call in another inspection.when dry out.. |
| 07/23/2026 |
Grading Progress ENGR |
|
Partial Pass |
1st lift of Asphalt Paving is starting today. AB Compaction tests completed and comply at 100%. Results will be submitted. Schedule another paving inspection for tomorrow and again the day before 2nd lift. If moving handicap parking and crosswalk to next bay south is not approved contractor is at risk. Okay to pave from first parking bay at SE corner of building going north and progressing around building. |