Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/21/2026 | Partial Pass | All 6 inch and 4 inch mainline reclaimed irrigation pipe on pages L4.3 and L4.4 is in place and correct to plan with poly plastic and thrust blocks in place at joints and angles per plan. OK to shade these main lines and begin backfilling before pressure test of mainline control wires and tape will be in place when finished backfilling. Trench is correct to plan. | ||
| 11/10/2025 | Not Ready | 11/10/25 Irrigation Main Trench for all 6" and 4" mains. Sections of the 6" trench west of the existing meters was not deep enough. Contractor will correct this trench. Otherwise trench dimensions are correct. Request inspection when mains are bedded and valves/ other equipment associated with mains are bedded correctly and sleeves are in place. |