Inspection History: For trash and recycling enclosures
| Date |
Description |
Inspector |
Results |
Comments |
| 02/18/2026 |
For trash and recycling enclosures |
|
Not Applicable |
Redundant inspection, not necessary. |
| 02/18/2026 |
For trash and recycling enclosures |
|
Partial Pass |
Material storage yard at SW corner of park: footing dimensions and reinforcement are good, slab excavation dimensions and reinforcement (#4 12" OC both ways) are good. Okay to pour footing and slab. |
| 03/16/2026 |
For trash and recycling enclosures |
|
Partial Pass |
3/16/26 SW Material Enclosers-Reinforcing correct to top of walls. Grout all reinforced cells and including bond beams with vibrator. |
| 08/26/2025 |
For trash and recycling enclosures |
|
Partial Pass |
East enclosure: bollards and reinforcement are good to pour slab, approach, and footing. Next inspection at 4 foot wall height, pre-grout. |
| 08/26/2025 |
For trash and recycling enclosures |
|
Partial Pass |
West enclosure: bollards and reinforcement are good to pour slab, approach, and footing. Next inspection at 4 foot wall height, pre-grout. |
| 09/04/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Wall construction and reinforcement are good; okay to grout up to 4 feet. Call next inspection when wall is at 6 ft, before final grout. |
| 09/04/2025 |
For trash and recycling enclosures |
|
Partial Pass |
West enclosure: Wall construction and reinforcement are good; okay to grout up to 4 feet. Call next inspection when wall is at 6 ft, before final grout. |
| 09/09/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Both enclosures: Wall construction and reinforcement are good; okay to grout to finish height. |