Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/09/2026 | Partial Pass | Good to pour the five pads on the west end of the park | ||
| 02/12/2026 | Failed | The sidewalk that the contractor wants to pour on the north west end of the project failed the density at 91%. Contractor will reschedule after the recompact the material. | ||
| 02/18/2026 | Partial Pass | 8' wide sidewalk on sheet C3.1 (NW quadrant), approximately 200LF running east-west: forms are set properly, ensure control joints are placed every 40' per PAG detail 200. Okay to pour. | ||
| 02/24/2026 | Partial Pass | Sidewalk forms surrounding dog parks entrances: forms and sub-grade are good, okay to pour. | ||
| 02/25/2026 | Partial Pass | Contractor is good to pour the for the sidewalk 160 lineal feet | ||
| 03/10/2026 | Partial Pass | contractor can pour about 150 lineal feet of sidewalk on the west side of the park I also stayed around for the weekly meeting |
||
| 08/18/2026 | Partial Pass | West Comfort Station/restroom sidewalk around building. ABC is correct. Submit compaction report to the portal. Forms, dowels, expansion material in place. Rebar in thickened edge correct. Slope good. Okay to pour pending good pictures of loose material removed from thickened edge and missing dowels in place. |