Permit: TD-DEV-1222-00078

Parcel: 12217278F


Addresses:

3233 E SPEEDWAY BL

Inspection Status: Partial Pass

Inspection History

Date Description Inspector Results Comments
05/19/2025 Partial Pass Contractors good to pour the small footing for the stem wall and the sidewalk area
07/17/2024 Not Ready Talk to the contractor the flat work and sidewalk area won’t be ready till tomorrow or maybe Monday
07/29/2024 Partial Pass Contractor is good to pour the sidewalk and the handicap ramp
08/20/2026 Not Ready Sidewalk cross slope and running slope under screen of outdoor theater does not comply, it is steeper than 5% so it effectively becomes a ramp and needs hand rail on both sides. landing at the top of this ramp also does not comply. One of the entryway landings from the box office/lobby does not comply. This needs to have the automatic door opening hardware removed and the entryway that does comply needs to have handicap symbols so that it is readily identified as the dedicated handicap door. Additional sidewalk can be poured to bypass the non-compliant landing here.
12/30/2025 Partial Pass Contractor needs to add hand railing on the exit on the north side exceeds the 5%
On the east exit of the theater the downspout needs to run into the parking lot area not onto the exit asphalt area