Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/15/2025 | ENGR Grading Final | Not Ready | 12/15/25 NW corner of Site- Temporary Silting Basin needs to be built per plan and detail 6/C800. There is only the headwall in place currently with a hole that needs to be compacted and defined per plan The basin top of the West Basin on the North side looks like it may not be at 89.88 at top opposite the curb cut inlet closest to the building. This top is also to have 2' of flat between its sides. Ensure the elevation and profile is correct before landscaping this area and placing DG. |
|
| 12/18/2025 | ENGR Grading Final | Passed | 12/18/25 Grading is currently being completed. The West Basin top is built correct to plan. EOR has approved changes to the Temporary Silting Basin. It has not been finished but should be built to the Engineers specifications.This is a Drainage structure and will be inspected as such at Final. |