Parcel: 140363550


Addresses:

5205 E VALENCIA RD


Inspection Status: Partial Pass

Inspection History: ENGR - Drainage Structures

Permit Number - TD-DEV-1124-00319

Inspection Description - ENGR - Drainage Structures

Inspection Status - Partial Pass

Date Description Inspector Results Comments
08/21/2025 ENGR - Drainage Structures Partial Pass Underground basins are being used, bedding, miraffe and cavity's have been installed per. plan and are correct.
08/22/2025 ENGR - Drainage Structures Passed 08/22/25, good to backfill this first area.
08/26/2025 ENGR - Drainage Structures Partial Pass 08/26/25, 2nd set of underground basins have been set, set is good to start backfill.
08/27/2025 ENGR - Drainage Structures Partial Pass 08/27/25, 2nd and 3rd set are good to backfill. Compaction with the moisture from recent rains is looking good.
09/18/2025 ENGR - Drainage Structures Partial Pass Okay to pour2 EF1’s & invert of junction structure
09/25/2025 ENGR - Drainage Structures Partial Pass Okay to pour headwall, catch basin, and junction lid.
09/26/2025 ENGR - Drainage Structures Partial Pass Okay to pour deck of junction structure and pipe collars.
10/01/2025 ENGR - Drainage Structures Partial Pass Inlet #1: reinforcement is good, okay to cap. Junction structure: reinforcement is good, okay to fill access port. Manhole #1: Reinforcement is good, okay to pour base.
10/02/2025 ENGR - Drainage Structures Partial Pass Contractor needs to patch all the way around the pipe that goes into the manhole and remove the existing pipe that’s inside. The manhole contractor will call in for reinspection tomorrow.
10/03/2025 ENGR - Drainage Structures Partial Pass Okay to install manhole
10/06/2025 ENGR - Drainage Structures Partial Pass 10/6/25
Manhole has been installed correct connection mortar clean. The Adjustment rings will need to adjusted when paving goes in. Looks high now. Reinspect when Paving complete.