Inspection Status: Not Ready

Inspection History: SITE - Stormwater Follow-up

Permit Number - TD-DEV-1124-00312

Inspection Description - SITE - Stormwater Follow-up

Inspection Status - Not Ready

Date Description Inspector Results Comments
06/27/2025 SITE - Stormwater Follow-up Not Ready Just finished the initial SWPPP today.
07/14/2025 SITE - Stormwater Follow-up Complete (Recurring) The Track Out on Gran Escalera is not functioning as designed. It Needs to be repaired as designed on the SWPPP plan. Gran Escalera needs to be swept and cleaned up due to Dirt/Sediment on the road.
07/16/2025 SITE - Stormwater Follow-up Complete (Recurring) Fix Trackout on Gran Escalera. Get SWPPP Box in place for book. See details in checklist.
08/04/2025 SITE - Stormwater Follow-up Complete (Recurring) Berms are being maintained. Trackout is functioning. There are stockpiles but they are being actively worked as the utilities are being installed.
09/19/2025 SITE - Stormwater Follow-up Failed 9/19/25
1. The track out at Lalas Way needs to be repaired to function as in intended currently there is a bypass with no rock on it.
2. The trench berm is not continuous on east side of site. It is interrupted approximately at lot 142 and there is another interruption north of that area. There is another area at Lot 15 on West side where there is no BMP. The SWPPP has continuous BMP’s around Perimeter.
3. The grade Limit T Posts and rope have been knocked over at the NE of site, just west of the Storm Basin. These need to be repaired.
4. On plan it shows OP outlet protection at low point at perimeter at SE end of Site. There is just Trench Berm at this point.
5. inspection Reports need to be kept in SWPPP book.