Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/14/2026 | Partial Pass | 1/14/26 Grout inspection. Perimeter of Phase. Grout ticket from Cemex Plant is good and shows slump 8 and complies. Contractor is vibrating Grout. Verts are wet set at 48" centers and at each side of expansion joint At 20' . |
||
| 01/30/2026 | Partial Pass | Perimeter site walls are finished are finished. Grout vibrated reinforcement correct. Contractor will begin on interior walls next. | ||
| 02/26/2026 | Passed | 2/26/26 Minimal wall requirements for screen wall footers between lots, on property lines dug at various lots in the North “4A” section. corner of Subdivision Are being met. Dims are 18" wide 12" deep with #4 verts at 48" OC, 1 #4 Continuous Hor. Chair spacers are being used for spacing and laps are 18". |
||
| 03/27/2026 | Partial Pass | 6 foot secondary theme wall per detail 8 L4.2 lots 64, 65, 81, 86-88 89, 99, 73, 72, 58, 50-57, 49, 162 and 163 built correct reinforcing correct. Okay to grout and finish walls. 6 foot perimeter slump theme wall per detail 7 L4.2 behind lots 34-39 and 40 built correct, reinforcing correct. Okay to grout and finish walls |
||
| 04/03/2026 | Partial Pass | Okay to pour wall footings at lots 24, 25, 31, 65-68, 62-64, 41, 73-79, 80, 81-86, 170-176 | ||
| 04/22/2026 | Re-inspection required | Reinforcing in footer at lot 58 reinforcing not finished. lots 59 to 61 reinforcing is OK but dirt needs to be cleaned out to maintain 3" clearance from reinforcing. he retaining walls that need to be grouted are not ready. The continuous bond beam at top of retaining wall is currently 1 #4. Detail 8 keynote 5 calls for 2 # 4s or 1 #5 |
||
| 04/24/2026 | Partial Pass | Retaining walls, lots 24,25,32,81-86,73-80,62-67,41: height and reinforcement is good, okay to grout . Lots 170-176: not stacked, not ready to grout. |
||
| 04/29/2026 | Partial Pass | Retaining wall footing between lots 47 & 48 and theme wall footing between lots 79 & 80: dimensions and reinforcement is good. Okay to pour footings. | ||
| 05/13/2026 | Partial Pass | Retaining wall footer lots 198 through 203 OK to pour. Footer for screen wall lot 197 and 184 OK to pour. Footer for retaining wall, 184 through 190 OK to pour. Screen wall footer 190 and 191 OK to pour. Screen wall footer, lots, 177 and 176 OK to pour. Screen wall footer 170 and 183 OK to pour. Screen wall footer lot 176 and 177 OK to pour. Pre-grout for retaining wall lots 170 through 176 Bond Beam in place at grade OK to grout. Next inspection will be pre-grout at top of wall. Screen wall footer for lot 170 and 183 OK to pour. Pre-grout inspection at top of wall for screen wall lots 169 through 165. Cut new verts for a lot 169 so it reaches top course. Vibrate all grout. Pre-grout inspection for retaining wall between lots 48 and 49. Bond beam at grade in place. OK to grout all cells two bond beam, vibrate all grout. Next inspection will be pre-grout for wall on top. Footer reinforcing must all be 3 inches clear of dirt with no loose dirt in footer… |
||
| 05/15/2026 | Partial Pass | Lots 62-58 fill all cells in retaining wall bond beam correct. Lot 80 ok to grout to top of walls 81 to 86 okay to grout to top of wall, vibrate all grout. | ||
| 10/30/2025 | Failed | 10/30/25 East side of Subdivision. Footer Rebar layout is not to plan for Partial View Fence. Columns are only being built at the property lines of each lot. Plan calls for them at 136" on center. |
||
| 10/31/2025 | Partial Pass | 10/31/25 North perimeter at Valencia. Slump block theme wall detail 7 L4.2 on-12 x 18" -Footer. 1 #4 continuous. Verts at 48", 2 every 20' for expansion joint. Do not forget to place open block at 10' OC for drainage as needed. Alternating theme walls with offset steel panel. |
||
| 11/13/2025 | Not Ready | 11/13/25 Some of the perimeter wall built is at B and B-1 lots. The detail in the DP says these lots shall have block removed at the corners for drainage. This needs to be addressed. When ready for pre grout inspection request inspection the day before. |
||
| 11/14/2025 | Partial Pass | 11/14/25 Contractor has been proceeding with the perimeter walls and building them to plan. This will be uploaded to permit. Today the Est sight wall is being grouted. The contractor will also vibrate grout in all reinforced cells, consolidating the grout. If mechanical vibrating is not done then puddling grout in 12” lifts is acceptable. |