Inspection Status: Partial Pass
Inspection History
| Date |
Description |
Inspector |
Results |
Comments |
| 02/03/2026 |
|
|
Partial Pass |
Sidewalk across South side of building is poured and within tolerances. Scuppers are not in place yet. Layout for curb ramp into parking lot is sloped correct. |
| 04/01/2026 |
|
|
Partial Pass |
Evaporative cooler pads, 3 on the south side, 1 at the NE corner plus 2 mini-split pads on the south side: dimensions, subgrade, and reinforcement are correct. Okay to pour 4+2 pads. |
| 05/12/2026 |
|
|
Passed |
|
| 06/20/2025 |
|
|
Partial Pass |
Heavy duty PCC slab to the West of main building: subgrade is correct (compaction results have been emailed), forms/depth is correct. Okay to pour (3am 6/24/25). |