Inspection Status: Partial Pass

Inspection History: Grading Progress ENGR

Date Description Inspector Results Comments
05/01/2026 Grading Progress ENGR Partial Pass Trackout rock insufficient. Open trenching still present. Some wedge curb has been installed. Inspections required. please email all compaction testing and utility acceptance to Joshua.garcia@tucsonaz.gov
05/29/2026 Grading Progress ENGR Partial Pass Subgrade is ok to place AB from main entryway straight West to the next intersection with all the parking bays. Subgrade is lower than grade hubs but this will be compesated with compacted AB that reaches correct level per plan. Again Rick engineering needs to approve subgrade and submit Compaction test results to the portal. .
06/09/2026 Grading Progress ENGR Partial Pass contractor is good to place AB on the south part of the project. Contractor also informed me that they’re going to use 5 1/2 inches of AB due to the rock that’s on the sub grade.
06/23/2026 Grading Progress ENGR Not Ready I walked with contractor and we string lined all areas where the AB needed to be approved. The final ab grade for phase 1 area by model homes and also lots 81-107. My tolerance was +/- .25". There were some areas that were too deep (closer to .5" than .25). . There was one spot I checked that was over .5" and needed .5" added in order to be within tolerance. This was the furthest SE parking Spaces on Desert Lab RD. Contractor told me he will fix these areas for a reinspection tomorrow. In order for these areas to meet tolerance.
06/24/2026 Grading Progress ENGR Partial Pass Desert Lab Rd to the entrance, N Boathouse LN south of Desert Lab RD and N Coville DR from Lot 21 to the Bullnose between the two parking bays between lots 96 and 81. AB is placed correct and compacted. Okay to pave this with 2.5" AC Mix #2.
10/13/2026 Grading Progress ENGR Partial Pass Subgrade is correct for remainder of streets and parking bays up to ROW on Santiago. Reveals, compaction and depths are correct for 2.5 over 4. Some areas along gutters are deeper but those will be compensated with extra AB. Okay to place AB. Schedule Paving inspection to check ABC when ready.