Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History: ENGR - Drainage Structures

Date Description Inspector Results Comments
05/21/2026 ENGR - Drainage Structures Partial Pass Drop inlet 9' X4' OD. Floor already poured but was approved by Rick Engineering. At basin 3 next to lot 81, connected to culvert #1 is per plan detail B pg 21 placed per survey and weir per survey and 24" chamfering at corners in place.
Okay to pour this Drop inlet walls.
05/26/2026 ENGR - Drainage Structures Partial Pass Correction to notes from 5/21 (I was wrong because drop inlet detail B/21 is used for both culverts). Drop is inlet next to lot 100, part of culvert #2. Otherwise notes are correct. Continuing north from drop inlet, culvert 2, next structure is catch basin detailed E/21. Floor is also poured previously but inspected by others and pictures taken. Dimensions of CB correct reinforcing correct, using PAG detail 309 and detail E pg. 21. Champfering correct. Grates/frames in place. Okay to pour walls. Of catch basin. At end of culvert 2 the footer for Headwall is correct to SD 6.3 (2 of 5) forms correct, reinforcing correct. Inverts to serval and correct to SD. Okay to pour footer.
05/28/2026 ENGR - Drainage Structures Partial Pass Headwall between lots 80 and 98 ok to pour after trimming verts that are within 1" of top of headwall.
06/12/2026 ENGR - Drainage Structures Partial Pass Okay to pour Culvert #1 outlet head wall footing.
06/24/2026 ENGR - Drainage Structures Not Ready Headwall Outlet into basin #2
Top of verts are .5 inch of top of head wall and top horizontal is also within 2" of the forms. Fix these and reschedule when ready.
06/25/2026 ENGR - Drainage Structures Partial Pass Headwall outlet into Basin 2- Clearance of reinforcing comply okay to pour
Floor of Drop Inlet at Culvert #1 okay to pour. Reinforcing and dimensions correct
06/29/2026 ENGR - Drainage Structures Partial Pass Drop inlet walls to Basin 2. Slot has been eliminated per engineer. Contractor will send me picture showing rebar with sufficient clearance at NW corner before pour. OK to pour walls.
07/06/2026 ENGR - Drainage Structures Partial Pass Type 2 sidewalk scuppers wall inspection. 3 cell scupper from basin C3 under sidewalk to smaller basin to the east. Also 1 single into Basin C3 Southeast of lot 3. Reinforcing correct and good for bond to scupper floor. Forms correct and .5" diamond plate good. Okay to pour these scupper walls.