Inspection History Details
Inspection Status: Partial Pass
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/19/2025 | ENGR Engineering Final | Partial Pass | Contractor needs to finish placing the DG in back of the apartments. Also needs to remove all the dead wiring. It’s coming up from the ground. Remove the fence that’s in the front and the construction side that did the front and separate one from phase 2 with fencing. | |
| 09/02/2025 | ENGR Engineering Final | Partial Pass | 9/2/25 Contractor will remove All Construction materials and debris from unfinished part of lot-Except waddle at west and south edges- because temporary fencing is being removed. call us back in for final when ready. Submit the Pool compaction test to the Demolition permit. Call in Final for demo permit when ready. |
|
| 09/04/2025 | ENGR Engineering Final | Passed |