Inspection Status: Failed
Inspection History: For trash and recycling enclosures
| Date |
Description |
Inspector |
Results |
Comments |
| 04/21/2025 |
For trash and recycling enclosures |
|
Failed |
Contractor did not install the vertical number for us per city detail. They need to put three number four in the corners two in the center for the double trash enclosure and two at the very end in the front. |
| 04/25/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Rebar placement has been corrected, ready for block. |
| 05/13/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Contractors to pour the floor for the trash enclosure |
| 07/11/2025 |
For trash and recycling enclosures |
|
Partial Pass |
Every looks correct dimensionally and the slab slope and clearances are good. The Gates are not typical and are not correct to TSM details. Figure 3a in section 8-01.9.0 calls for 1/8” steel plate with a tube steel cross bar frame. |
| 07/29/2025 |
For trash and recycling enclosures |
|
Partial Pass |
|
| 08/19/2025 |
For trash and recycling enclosures |
|
Passed |
|