Inspection History Details
Inspection Status: Passed
Inspection History: SITE - Stormwater Setup and Controls
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/15/2026 | SITE - Stormwater Setup and Controls | Passed | NOI in place SWPPP board and book are in place next to gate. Lock Combo 4750 Eagle Rock is responsible party Track out good Wattle in place. |
|
| 08/17/2026 | SITE - Stormwater Setup and Controls | Passed | Storm Water Initial inspection completed previously. -Stormwater biweekly inspections need to be set up. -Add wattle across potential outflow to basin at southeast corner of site. Currently it looks like storm water would flow into the adjoining basin on other side of fencing. Recondition or add rock to the Trackout at construction entrance. Rock is getting compacted and not functioning as designed. -It has been 30+ days since last routine SWPPP inspection. You should be occurring every two weeks or after a Storm event during monsoon season. Otherwise site BMP's are okay |