Inspection History Details
Inspection Status: Not Ready
Inspection History: Final inspection to ensure all landscape and water harvesting SITE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/06/2026 | Final inspection to ensure all landscape and water harvesting SITE | Not Ready | Discussed water harvesting basin. Hydroseed will be required. | |
| 06/03/2026 | Final inspection to ensure all landscape and water harvesting SITE | Partial Pass | 6/3/26 Basin 1 correct-except- Outlet Weir of Basin 1 next to/onto Ganley Rd. It is not clearly drawn to show what the intention of where water should go after it crosses weir. Looks like it will go down to ditch along road. Shouldn't this area should have riprap to prevent erosion? |
|
| 07/14/2026 | Final inspection to ensure all landscape and water harvesting SITE | Passed |