Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Parcel: 133231470


Addresses:

7333 E ROSEWOOD ST


Inspection Status: Not Ready

Inspection History

Permit Number - TD-DEV-0924-00272

Inspection Description -

Inspection Status - Not Ready

Date Description Inspector Results Comments
03/06/2026 Not Ready 3/6/26 6 inch PCCP Driveway apron from the asphalt in private road to the PAAL. PAAL will also be 6 inches PCCP poured later. Contractor wants to reschedule inspection for Monday.
Compaction in Subgrade and AB comply. Submit compaction test results to the portal. Currently WWM 6”x6” in place. There is no PCCP Detail to reference. There's no expansion joint material at curbs. I'm asking him to put a thickened edge where it meets the asphalt. 3 inches by a shovel width so 9 inches total depth. Add one #4 rebar at thickened edge. Construction joints, every 20 feet and expansion joints every 40 feet minimum.
03/09/2026 Partial Pass 3/9/26
Forms, density reports, expansion joint material, spacing, reinforcing and 6” depth correct. Ensure crosswalk cross slope remains 2% or less. Place expansion joint material around Cox cable box full depth of pour. Okay to pour PCCP driveway apron, phase one.