Inspection Status: Partial Pass

Inspection History: For trash and recycling enclosures

Date Description Inspector Results Comments
02/20/2026 For trash and recycling enclosures Partial Pass Dumpster enclosure footing excavation and reinforcement are good. Okay to pour footing.
03/09/2026 For trash and recycling enclosures Not Ready 3/9/26
Contractor built the walls all the way up to 6; and put weep holes at the bottom but number four verts stop at the first lift. The #4 fours go in all the cells with weep holes and are continuous up to the bomb beam at the top of the wall. also the column for gates. Reschedule when you're ready...
04/08/2026 For trash and recycling enclosures Partial Pass Trash enclosure slab and approach: reinforcement and dimensions are good. Okay to pour.