Inspection Status: Partial Pass

Inspection History

Date Description Inspector Results Comments
02/26/2025 Partial Pass Contractor is good to pour the footer for the head wall on the west side of the project
03/12/2025 Passed
11/15/2024 Partial Pass Bedded acceptable. ready to cover with additional sand cover prior to actual backfill.
11/20/2024 Partial Pass contractor back storm drain pipe. Josh Garcia OK to backfill with bedding material on top of the pipe 1 foot and then continue to backfill with native material
11/22/2024 Partial Pass okay to backfill E-W run of pipe.
11/25/2024 Partial Pass Contractor is good to lay pipe going east and one going south
12/03/2024 Partial Pass Contractors installing 12” x 52’ of HD pipe on the north west corner of the project. Good to backfill.