Inspection Status: Partial Pass
Inspection History: ENGR - Drainage Structures
| Date |
Description |
Inspector |
Results |
Comments |
| 01/30/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
Contractor can pour the footings for the trash enclosure |
| 02/06/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
Contractors good to grout the trash enclosure |
| 02/19/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
Contractors good to pour the floor and the apron for the trash enclosure |
| 03/12/2025 |
ENGR - Drainage Structures |
|
Passed |
|
| 11/25/2024 |
ENGR - Drainage Structures |
|
Partial Pass |
Contractors good to pour the two floors for the manholes West of the existing buildings |