Inspection Status: Not Ready

Inspection History: PDSD Engineering Division Pre-Construction SITE

Date Description Inspector Results Comments
07/06/2026 PDSD Engineering Division Pre-Construction SITE Not Ready Representatives from Civil contractor Borderland and other general contractor also working on the same DP permit Supreme as well as Chase need to be present at Pre Construction meeting. A satisfactory SWPPP site plan with BMP’s that are included in plan is required. A SWPPP will not function without BMPs that are set up and working correctly.
07/08/2026 PDSD Engineering Division Pre-Construction SITE Canceled Contractor needs more time to get BMP’s in place and to coordinate with other parties for meeting.
07/14/2026 PDSD Engineering Division Pre-Construction SITE Passed BMP's are in place, SWPPP board is in place, SWPPP book in office w/ NOI.
Survey in place, Pads certified. Rough grading is being done almost complete.. Strormdrain stakes are in place.
Inspections needed:
Grading inspections
Paving inspections
Flat work, sidewalk inspections
Drain drainage, structure inspections
Landscaping, appearance and function final
Striping and signage inspections
Engineering final