Inspection Status: Partial Pass
Inspection History: For trash and recycling enclosures
| Date |
Description |
Inspector |
Results |
Comments |
| 07/29/2026 |
For trash and recycling enclosures |
|
Partial Pass |
Refuse enclosure footing: dimensions, reinforcement, and layout is correct. Okay to pour footing. |
| 07/31/2026 |
For trash and recycling enclosures |
|
Partial Pass |
Refuse enclosure wall pre-grout: block and reinforcement are correct to 48 inches. Okay to grout first lift. |
| 08/04/2026 |
For trash and recycling enclosures |
|
Partial Pass |
OK to grout second lift. Bond beam in place correct. |
| 08/10/2026 |
For trash and recycling enclosures |
|
Partial Pass |
Floor forms, reinforcing mat and bollards Okay to pour. Use expansion joint filler material where floor meets the wall. |