Inspection Status: Partial Pass
Inspection History: ENGR Paving
| Date |
Description |
Inspector |
Results |
Comments |
| 10/08/2026 |
ENGR Paving |
|
Partial Pass |
Okay to pave South parking Bay up to where grading is incorrect on east end-Stop approximately 40' west of incorrect curb at Refuse enclosures. This area is less than 1.5% slope downgrade to north that is on plan. Okay to pave Handicap parking bay and bay to the east of handicap parking bay. The other bays need to be corrected and rolled and approved. The PAAL is not ready. It is loose and not ready to be string lined. This was discussed with Contractor. Reschedule when ready. |
| 10/09/2026 |
ENGR Paving |
|
Partial Pass |
Continue rolling 3” AC profile areas - Continue prepping parking bays - when ready - and compaction passes - okay to pave. |