Inspection History Details
Inspection Status: Partial Pass
Inspection History
Permit Number - TD-DEV-0723-00335
Inspection Description -
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/04/2025 | Partial Pass | 9/4/25 East wall screen wall-32"/4 courses high. Footing width and Depth are correct to SD 109. Reinforcing correct. Okay to pour footer. Use horizontal reinforcement @ 16 oc. Call us out for pre grout inspection before grouting. |
||
| 09/09/2025 | Partial Pass | Contractors good to pour the footer for the 30 inch wall on the north end and the one on the northwest end | ||
| 09/10/2025 | Partial Pass | Contractor formed up of retaining wall footer on the speedway side and me that wasn’t ready yesterday. It’s good to be poured for today. | ||
| 09/11/2025 | Partial Pass | Inspected the footer for the wall on the south east corner of the building good decor | ||
| 09/16/2025 | Partial Pass | Contractor needs to remove the broken block in the selves of the 30 inch walls on the north east end. Contractor also needs to add more number four bars on those 30 inch wall on the north west end. | ||
| 09/17/2025 | Partial Pass | Contractor, good to grout all the walls in front of the building |