Inspection History Details
Inspection Status: Partial Pass
Inspection History: Grading Progress ENGR
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/09/2026 | Grading Progress ENGR | Partial Pass | AB is good, blue tops are in place, compaction tests are happening soon. Okay to pave pending passing compaction results. | |
| 06/25/2026 | Grading Progress ENGR | Passed | Site walk to check on overall condition and identify any issues. Sidewalks and flatwork slopes are within required tolerances. ADA parking slopes are within required tolerances. Ensure bottom of signs are 7 feet above sidewalk surface. Irrigation laterals should be trenched to 18 inches deep. Landscape areas should be depressed up to 6 inches. (Except within 10 feet of building foundation) Basin outlet structures and downspout splash pads not yet installed. Southeast corner of building needs to have positive drainage away from the building. Rainwater basins need to be free of standing water by 24 hours following a rain event. Refuse enclosure needs a method to secure the doors in the open position. |