Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: TD-DEV-0625-00156

Parcel: 132191010


Addresses:

4697 S CAMPBELL AV

Inspection Status: Partial Pass

Inspection History

Date Description Inspector Results Comments
05/12/2026 Partial Pass contractors installing HDP pipe for the overflow on the basin on the east side. Informed the contractor that they need bedding sand a foot on each side of it and to give us a call before they backfill.
05/27/2026 Partial Pass 5/27/26
Drainage structure inspection. 3 out of the 5 spillways are good to detail 10/C601. Contractor will send pictures of the 2 that need to be corrected before approval for pour.
Basin 1 has a drop inlet catch basin. PAG SD 309 Type 4 single. Reinforcing is not correct to SD 309. Keynote 4 on C300 also calls for 6" orafice in west wall rim at .75' above invert of drain pipe out. Basin is to pond .75' Forms and reinforcing need to be corrected. Grate Frame also is missing. Okay to backfill pipe 12" HDP when ready. Do not pour this Catch Basin. Reschedule Drainage structure inspection when ready.
06/09/2026 Partial Pass okay to pour catchbasin/outlet structure in water harvesting basin.
07/07/2026 Passed