Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Partial Pass
Inspection History
Permit Number - TD-DEV-0624-00187
Inspection Description -
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/07/2025 | Partial Pass | 07/07/25, pipe was partially backfilled so I could not check entire length. This pipe goes from Tucson blvd to the Intertwine dry well system. There are 2 more pipes to install. |
||
| 07/09/2025 | Partial Pass | 74 LF run from manhole towards Tucson blvd is installed and sloped according to plans - okay to backfill. | ||
| 07/10/2025 | Partial Pass | 3 pipes feeding into Drywell: pipe is accurate to plans, slope is good, okay to backfill. | ||
| 07/17/2025 | Not Ready | 7/17/25 Three catch basins SDCB#1 thru #3 Pipe type and dimensions are correct. Precast Catch Basins match plans. Rims and Invert Elevations are all higher than plan. The elevations are not to plan making slope of pipes not to plan. They are all too steep. Inverts and Rims need to be to plan before pipes are connected to CB's. These elevations need to be verified by surveyor and corrected to plan. 8" PVC may need to be exposed and reconnected to Drywell. Drywell elevation and CB elevation need to be verified and corrected if nessisary. Basin Elevations also need to be verified . |