| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/13/2026 | Grading Progress ENGR | Not Ready | Subgrade north of loading docks is ready for AB with a few touch ups discussed with contractor. Area as it approaches the ROW is crowned at middle between curbs and needs to be fixed and turn around area to the east of entry way is not complete. Reschedule inspection when ready. | |
| 10/14/2026 | Grading Progress ENGR | Partial Pass | Okay to place ABC in parking area and turn around. | |
| 10/22/2026 | Grading Progress ENGR | Partial Pass | Grading is almost complete for Ist phase.. For Paving: Contractor will fix areas marked on AB and the area around outlet from basin and Western section of North Loading/Parking lot. South Turn Around also needs some attention to ensure all drainage reaches the basin inlet. Reschedule for tomorrow. |