Inspection Status: Not Ready
Inspection History
| Date |
Description |
Inspector |
Results |
Comments |
| 02/13/2026 |
|
|
Not Ready |
Wall along West side, rebar not ready. |
| 02/17/2026 |
|
|
Partial Pass |
Wall footing along West side: excavation and reinforcing bar is correct, okay to pour footing. |
| 04/30/2026 |
|
|
Partial Pass |
Site wall on north side: footing dimensions and reinforcement are good, okay to pour. |
| 06/24/2026 |
|
|
Partial Pass |
Vacuum footing cages are good pending documentation from Engineer of Record that it's acceptable to epoxy the rebar into the bottom foundation. (This inspection excludes electrical underground) |
| 07/09/2026 |
|
|
Passed |
7/8/26 - Site walls are complete. Grouted rip-rap along South (existing) retaining wall is all that remains. |