Inspection History Details
Inspection Status: Not Ready
Inspection History: For trash and recycling enclosures
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2026 | For trash and recycling enclosures | Not Ready | 3/19/26 Footer refuse enclosure is for 16 foot wide wall. I don't see a TSMR for modifying the refuse enclosure in the plan details that shows a standard single refuge enclosure with 13'4" width. Do not pour this footer until this is result. |
|
| 03/19/2026 | For trash and recycling enclosures | Partial Pass | 3/19/26 I received Email from Any Vera Confirming the wider Refuse Enclosure is fine for recycling. Okay to pour footer after I receive pictures showing adjustments discussed with contractor -2 rebars at wall ends and no dirt within 3" of rebar |
|
| 03/24/2026 | For trash and recycling enclosures | Partial Pass | 3/24/26 Refuse Enclosure 1st lift walls grouted. Wall is finished to top course. Okay to grout to bond beam at top and finish walls. Schedule inspection for bollard footers before pouring bollards. Schedule inspection before pouring floor. They can be poured at the same time with one inspection if it is correct if you prefer. |