Inspection History Details
Inspection Status: Partial Pass
Inspection History: For trash and recycling enclosures
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/18/2026 | For trash and recycling enclosures | Partial Pass | 3/18/26 Refuse Enclosures walls are built to 8' per per detail 1/S2.1 in proposed revision with correct reinforcing that is visible. Attached Storage Shed walls are built to 9' and to same detail. Contractor may grout these walls but is at risk if revision is not accepted. |
|
| 04/03/2026 | For trash and recycling enclosures | Partial Pass | Both trash enclosure slab and approach have correct dimensions and reinforcement. Okay to pour slabs and approaches. | |
| 04/08/2026 | For trash and recycling enclosures | Partial Pass | Refuse enclosures' construction is in accordance with approved plan revision for wall height. Walls, slab, apron, and bollards are complete and acceptable. |