Inspection History Details
Inspection Status: Not Ready
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/16/2025 | Not Ready | Contractors going to reschedule when ready | ||
| 12/18/2025 | Partial Pass | Contractors good to pour the footing through the retaining wall on the west side of the building | ||
| 12/19/2025 | Partial Pass | Refuse enclosure/retaining wall footing: reinforcement, dimensions, and compaction are good. Storage area added to East of enclosure is built to the same detail as the main enclosure, currently at-risk pending plan revision. | ||
| 12/23/2025 | Partial Pass | Retaining wall at west side: reinforcement is correct. Okay to grout. | ||
| 12/30/2025 | Partial Pass | Refuse enclosures (2) are okay to grout the first lift (<4 foot). Toe for grouted rip-rap along North edge: depth and reinforcement are good, okay to pour. |