Inspection History Details
Inspection Status: Partial Pass
Inspection History: ENGR Paving
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/25/2026 | ENGR Paving | Partial Pass | Shared access area: subgrade north of valley gutter is good, okay to place AB here. Existing AB south of valley gutter was pumping, removed AB, replace section of subgrade, replace AB. Schedule to check AB finish conditions prior to paving. | |
| 03/31/2026 | ENGR Paving | Passed | Shared access driveway on the South: AB placement, depth, and compaction are good. Okay to pave this section. | |
| 04/30/2026 | ENGR Paving | Partial Pass | Subgrade elevations, compaction, and slopes are good throughout, okay to place AB. | |
| 05/08/2026 | ENGR Paving | Partial Pass | Parking lot paving: AB overall depth, slopes, and compaction are good. Okay to pave. Northwest PAAL radius curb does not match plan elevations, slopes the wrong way, surface water needs to be conveyed off of the asphalt while maintaining necessary curb reveal. |
|
| 05/19/2026 | ENGR Paving | Passed | Paving is complete in accordance with approved plans. |