Inspection Status: Partial Pass
Inspection History: ENGR - Drainage Structures
| Date |
Description |
Inspector |
Results |
Comments |
| 01/28/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
Contractor called in the wrong inspections contractor needed me to inspect the footer for the trash enclosure. Everything’s good. |
| 02/18/2025 |
ENGR - Drainage Structures |
|
Partial Pass |
Contractors good to grow up to 6 foot |
| 02/21/2025 |
ENGR - Drainage Structures |
|
Passed |
Trash enclosure slab and approach good to pour, this also included the grout inspection and the weep holes we’re visible 02/21/25 |