Inspection Status: Partial Pass
Inspection History: ENGR Paving
| Date |
Description |
Inspector |
Results |
Comments |
| 10/01/2026 |
ENGR Paving |
|
Partial Pass |
AB has been placed and compaction testing comply. Blue tops in place and correct AB should be rolled in areas that are drying from storm earlier this week and any other loose spots and along curb edges. From curb corner of grading detail 1 over to WHIA retention island AB needs to be evened out in order that depth of AB is 8.5" off of top of curb. Ensure that all storm water in this area flows to inlets to prevent puddling. AB needs additional rolling where it meets concrete walkway at south end paving. Okay to pave pending pictures if areas mentioned addressed and rolled smooth. |