Inspection History Details
Inspection Status: Partial Pass
Inspection History
Permit Number - TD-DEV-0425-00116
Inspection Description -
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/04/2026 | Partial Pass | 1. Sidewalk forms along west side of building are correct, okay to pour. 2. Sidewalk parallel to entrance drive on Hedrick: okay to create a landing (>2% slope) at the parking lot side and slope the remaining sidewalk down to the public sidewalk at less than 5% running slope. 3. Curb ramp at ADA parking: okay to form with sidewalk landing flush with asphalt (slope away from the building, less than 2%) and then ramps on either side with running slope less than 8.33%. (Similar to PAG 207 TYPE 3) 4. Sidewalk along north side of building is finished within acceptable tolerances. |
||
| 02/10/2026 | Re-inspection required | 2/10/26 Flat work and in front of building and behind building poured already. This sidewalk is flat and slope complies. Curb ramp at SW of building is formed and complies. Okay to pour the sidewalk and ramp in this area. The sidewalk ramp on other side of PAAL just east of the Refuse Enclosures needs to be Redesigned. It needs to have positive slope from where it meets the asphalt in order to keep water drainage off of the sidewalk to comply... It looks as if this will cause a greater than 5% running slope down to the ROW sidewalk. This sidewalk may need handrail to comply. Engineer needs to redesign this so it will work and be built to plan. |
||
| 02/12/2026 | Partial Pass | Sidewalk from parking lot to ROW along Hedrick: okay to slope ramp at top down towards parking lot so long as it doesn't affect the flow of stormwater. Also okay to make 'ramp' at the top close to level (err on the side of sloping towards asphalt) to maintain asphalt elevations and keep sidewalk under 5% running. | ||
| 02/24/2026 | Partial Pass | Sidewalks are poured and are within acceptable tolerances. | ||
| 12/18/2025 | Not Ready | Sidewalk ready for inspection is ROW |