Permit: TD-DEV-0425-00111

Parcel: 13014023A


Addresses:

4220 E 22ND ST

Inspection Status: Passed

Inspection History: PDSD Engineering Division Pre-Construction SITE

Date Description Inspector Results Comments
06/05/2026 PDSD Engineering Division Pre-Construction SITE Passed Meeting held on-site to discuss scope of project and inspection requirements. Advised that they get access to/keep on site a copy of the stamped plans to ensure that the most up to date drawings are being used. Below are the inspections needed for this project.
Stormwater Initial: To confirm horizontal controls and SWPPP measures. (Also opens up inspections for site work)
Sidewalk/Flatwork: For sidewalks, curb ramps, and valley gutter.
Paving: For subgrade, AB, and asphalt.
Striping & Signage: for lot lines and ADA signage.
Landscape Final: for plantings and irrigation.