Inspection Status: Not Ready
Inspection History: ENGR Paving
| Date |
Description |
Inspector |
Results |
Comments |
| 09/23/2026 |
ENGR Paving |
|
Not Ready |
|
| 09/24/2026 |
ENGR Paving |
|
Not Ready |
Parking Bays are not finished and the service drive is not ready- AB levels are not correct or consistent. Compaction testing needs to be done. |
| 09/25/2026 |
ENGR Paving |
|
Partial Pass |
Okay to pave service drive pending pictures of area at temporary fencing at north end cleaned up and compacted, too much loose aggregate here. Also curb transition area south of the curb ramp on west side this area of AB to about half way to middle of drive needs to be shaved. East bay is not ready but bay in front of Larry H Miller arch with ramp okay to pave. Bay to west not ready either. Schedule inspection for Monday to approve the 2 bays not ready. |