Inspection Status: Partial Pass
Inspection History: Grading Progress ENGR
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/29/2026 | Grading Progress ENGR | Partial Pass | remove material okay to begin installing AB on south drive. | |
| 10/23/2026 | Grading Progress ENGR | Partial Pass | Area of Heavy duty concrete on East side of building and west of asphalt. ABC needs to be adjusted 1" +/- at some of the curb reveals for a 6" curb and 7" of Concrete pavement. Use plate tamper when adjusting the reveals and to tamp any loose areas. Ensure depth of concrete will reach 7" . ABC and subgrade density complies. Submit results to the portal. When ABC depth corrected okay to place #3 rebar @ 18” OC each way, with dobies/chairs for correct clearance over the AB. Subgrade for Asphalt still need work to be complete and ready for AB |
|
| Grading Progress ENGR | Scheduled |