Parcel: 13216600A


Addresses:

4410 S PARK AV


Inspection Status: Partial Pass

Inspection History

Permit Number - TD-DEV-0423-00198

Inspection Description -

Inspection Status - Partial Pass

Date Description Inspector Results Comments
01/22/2025 Partial Pass Okay to grout wall on West side of site.
02/07/2025 Partial Pass Vertical rebar on site wall on south side is in ready for grout.
Bond beam at top of wall on north side and north west corner at Stormwater basin is also in and ok.
02/10/2025 Partial Pass Rebar verts are in place and hors at bond beam at top are all in place at top of wall. This condition starts at 200 ft north of corner of Fair and Ralph Martinez Way. (S of this point is unfinished). It continues north to NWCorner of site and continues all the way around to NE corner of site. All this wall is ready to be finished grouted.
02/12/2025 Partial Pass Remaining Site Wall at SE corner of site has verts and bond beam rebar in place at top of wall ready for grout. This condition continues from corner east over to the driveway access off of Fair.
03/17/2025 Partial Pass Ready to proceed with grout.
05/21/2025 Partial Pass Second lift of grout ready to pour for wall. Reinforcing correct.
Vibrate all filled cells.
Wall section is 150 yards long on south end property starting by the track out to the finished wall.
10/24/2024 Partial Pass Footings and rebar passed
10/24/2025 Partial Pass 10/24/25
Footer for masonry wall starting just east of south driveway Running east to basketball court returns north to corner of building. Footer dimensions, correct. Two continuous number fours and verts at 32 inch OC (plan calls for 48"). Three verts in the corner. Two at wall ends. And two at each side of expansion joints. At footer adjacent to basketball court, grade is separation is close to 2 feet in this area. A third continuous number four is added, and all cells will be grouted to grade. OK to pour footer pending picture of third continuous.
10/28/2024 Partial Pass footing accepted. okay to pour footing.
10/30/2024 Partial Pass good to pour footing on south fence line
11/07/2025 Partial Pass 11/7/25
1st lift of wall at SE corner from driveway to building complete. Horizontal reinforcement correct. Fill all cells below grade. Vibrate all grout. Schedule inspection for bond beam when ready.
11/13/2024 Partial Pass
11/26/2025 Partial Pass 11/26/25
OK to grout 2nd lift of walls Southeast of building. Vibrate all grout, bond beam and vertical reinforcing correct. East wall is solid grout West wall will just be grouted at verts and one beam.