Inspection History Details
Inspection Status: Partial Pass
Inspection History: For trash and recycling enclosures
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/19/2026 | For trash and recycling enclosures | Partial Pass | 3/20/26 Footer for Refuse Enclosure. Correct to plans and details in the Bldg. plans S1.0, S2.1, S2.2. Footer dimensions and reinforcing correct for 6' walls per detail 8 on S2.1 #6 verts @ 24'OC. #5 continuous Horz. Lapped at 54" per lap table. Schedule pre grout inspection when ready with 1st lift so we can check vert laps (43") and bond beam. Okay to pour footer and bollards. |
|
| 04/01/2026 | For trash and recycling enclosures | Not Ready | First lift not complete. 1/2 way done. Need to see bond beam at 5th course. Wall will have #5 bond beam in 1st, 5th and top courses of wall. | |
| 04/02/2026 | For trash and recycling enclosures | Partial Pass | 1st lift complete w/ #5 bond beam. Okay to grout 1st lift. Grout solid, vibrate all grout. Schedule pre grout inspection before grouting 2nd lift, also before pouring floor. | |
| 04/06/2026 | For trash and recycling enclosures | Partial Pass | Okay to grout 2nd Lift of wall. Vibrate all grout. Schedule inspection For us to look at reinforcing and forms for floor be pouring. Also schedule inspections for Flatwork and Ramps to check forms and Paving inspections when subgrade is ready for ABC.. | |
| 04/23/2026 | For trash and recycling enclosures | Not Ready | Bollard footers need to be cleaned off of about +/- an inch of dirt on top of the concrete that was used to set the bollards previously. Footers should be continuous, the footers are reinforced and rebar needs to be protected.. Ensure rebar is 3” clear of dirt. |
|
| 04/24/2026 | For trash and recycling enclosures | Partial Pass | Okay to pour SOG | |
| 05/01/2026 | For trash and recycling enclosures | Partial Pass | Okay to pour apron of Refuse Enclosure. |