Inspection History Details
Inspection Status: Partial Pass
Inspection History: ENGR Paving
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/06/2026 | ENGR Paving | Partial Pass | 5/6/26 This is a paving inspection for AB in parking lot. Parking spaces 3" thick, drive area 4" thick. Survey hubs are in place and okay. AB Compaction tests ok, Submit to Portal. Some areas of concern were shaved and others raised. A Roller compacted these areas. Handicap parking also was checked for slope. There is a curb ramp that is missing at crosswalk to Refuse Enclosure. Also a curb cut to a basin is missing on east side of parking lot. North East corner of parking lot curb is broken. These curbs will need to be repaired/repoured. Okay to Pave with contractor at risk if any areas do not drain correctly per grading sheets. Do not schedule inspection For AB on same day as laying asphalt again. It needs to be inspected for day before. |