Inspection Status: Partial Pass
Inspection History: ENGR Paving
| Date |
Description |
Inspector |
Results |
Comments |
| 07/07/2026 |
ENGR Paving |
|
Partial Pass |
Paving layout, compaction, & slopes are good. Most recent approved plans call for 4 inches of asphalt, intent is to lay 2.5 inches to match existing conditions. This change needs to be approved by the City; asphalt pour is at-risk prior to approval. |
| 07/30/2026 |
ENGR Paving |
|
Partial Pass |
Paving layout, compaction, & slopes are good. Appropriate approvals have been obtained to proceed with "match existing" for asphalt sections. Okay to pave. |
| 10/30/2026 |
ENGR Paving |
|
Partial Pass |
Okay to pave and patch trenches w/ 2" PAG mix 2 asphalt. Send pics with clean 2" reveals with tack oil at curbs and seams. Also picture of 4" sidewalk forms with expansion joint material. |
| 11/19/2026 |
ENGR Paving |
|
Passed |
Paving Complete and correct |