Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: ENGR Paving
| Date |
Description |
Inspector |
Results |
Comments |
| 07/07/2026 |
ENGR Paving |
|
Partial Pass |
Paving layout, compaction, & slopes are good. Most recent approved plans call for 4 inches of asphalt, intent is to lay 2.5 inches to match existing conditions. This change needs to be approved by the City; asphalt pour is at-risk prior to approval. |
| 07/30/2026 |
ENGR Paving |
|
Partial Pass |
Paving layout, compaction, & slopes are good. Appropriate approvals have been obtained to proceed with "match existing" for asphalt sections. Okay to pave. |