Inspection History Details
Inspection Status: Partial Pass
Inspection History
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/07/2026 | Partial Pass | contractor started excavating on Andrada Road for the articulated crossings of the washes. Informed the contractor to station the beginning of the articulated block and at the end of each crossing. | ||
| 05/18/2026 | Partial Pass | calling me brave from Wilmont Road to station 18+00 removing the existing CRP pipes I’m gonna replace them with RCP’s | ||
| 05/21/2026 | Partial Pass | contractor moved 57 lineal feet of CMP and gonna replace it with 30 inch RCP‘s. Contractor also started grading for subgrade from28+00 to Wilmont rd |
||
| 06/23/2025 | Partial Pass | Contractor continues to cut in the road and placing the rock from Wilmont West for about a quarter mile on the roadway | ||
| 07/21/2025 | Partial Pass | I drove the road. It’s still in good condition after all the rains we’ve had. No concerns at this time on the grading |