| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/29/2025 | Partial Pass | 7/29/25 Submit Subgrade compaction tests under sidewalk to the permit in the portal. The area of sidewalk in front of the entrance of the school with the bollards needs an expansion joint bituminous filler material installed the full thickness of the sidewalk. The 50’ max between expansion joints is exceeded in this area. The sidewalk area in front of the Refuse Enclosures also needs to be addressed whether it needs expansion joints. this area also exceeds 50’. Call in grading Inspections and Paving inspection before you pave but after you are done putting down the abc. |
||
| 07/30/2025 | Partial Pass | 7/30/25 Rebar is in place in toe of curb. Curb ramp correct. This is the last section of sidewalk and curb at entrance/exit on 12th Ave. Okay to pour. No Need for expansion joints in Flatwork in front of refuse containers. Flatwork is correct with remesh reinforcing. Call in Paving inspection for Friday. Sweep up dirt on S 12th Avenue. Add Rock to the Trackout. |