Inspection Status: Partial Pass
Inspection History: ENGR Paving
| Date |
Description |
Inspector |
Results |
Comments |
| 08/01/2025 |
ENGR Paving |
|
Partial Pass |
Parking lot subgrade: South half AB is installed to specs, grade/slope is good, compaction is >100%, blue tops are set; okay to pave the portion South of the concrete drainage. North half will need inspected prior to paving to verify finish conditions. |
| 08/04/2025 |
ENGR Paving |
|
Partial Pass |
AB is at proper depth and compaction throughout, blue tops are in place. Okay to pave entire parking lot and drive lanes. |
| 08/15/2025 |
ENGR Paving |
|
Passed |
8/15/25 Paving looks correct. Levels on curbs and curb cuts look consistent and good. Drainage looks good to the intent. Submit Cert confirming Pcc/cot sspi #406 mix #2 to portal. Slopes at ADA Parking and aisles comply. |