Inspection Status: Not Ready

Inspection History: BULD - Electrical Clearance

Date Description Inspector Results Comments
11/17/2026 BULD - Electrical Clearance Not Ready 11-17-26 Reschedule inspection for DGL meter socket .
Reschedule power kill per TEP.
11/19/2026 BULD - Electrical Clearance Passed 11-19-26 Verbal given to TEP at 10:38am MSA DGL clearance approved.
Solar Pv system inspected, new solar new battery, installed per plan. Approve clearance for DGC/BAT