Inspection Status: Passed

Inspection History: BULD - Electrical Clearance

Date Description Inspector Results Comments
02/02/2026 BULD - Electrical Clearance Passed 02/02/2026
Clearance TEP DGC/BAT. Verified revision and Solarapp Checklist dated 1/9/26 matches field installation.
12/08/2025 BULD - Electrical Clearance Partial Pass 12/08/2025
Clearance TEP INCR for 200A MPU cutover. Partial pending solar final.
12/24/2025 BULD - Electrical Clearance Not Ready 12/24/2025. Not ready install not per plan. Provide a revision or corrections need to be made in the field.