Inspection Status: Partial Pass
Inspection History: BULD - Electrical Clearance
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/06/2025 | BULD - Electrical Clearance | Partial Pass | Partial for the 200A service panel upgrade- INCR Clearance was called into TEP at 1:00pm Pending solar final and solar plan revision |
|
| 08/06/2025 | BULD - Electrical Clearance | Re-inspection required | 8/6/25 Main panel not per plan, 100A Main disconnect and 125A Busbar is requested. |
|
| 08/26/2025 | BULD - Electrical Clearance | Passed | Approved solar and battery - DGC/BAT Clearance to TEP is required for the solar meter | |
| 08/26/2025 | BULD - Electrical Clearance | Passed | Approved solar and battery - DGC/BAT Clearance to TEP is required for the solar meter |